Gas Turbine Inlet Air Cooling: Why It Pays And How It Works

Knowledge base

In short

Gas turbine inlet air cooling cools the air before it enters the compressor, because hot air is thin and reduces the output and efficiency of the turbine on warm days. Cooling it wins back power when the grid needs it most. Several methods exist, and the right one depends on the climate and the plant.

A gas turbine is a machine that moves air: its output depends on the mass of air the compressor can swallow, and hot air is thin air. On a hot afternoon a heavy-duty turbine delivers clearly less than its rating, and its efficiency gets worse - exactly when the grid needs the power most. Inlet air cooling cools the air before the compressor and wins much of that output back. This guide explains the methods, the role of the finned inlet coil, and what such a coil must survive.

Why Temperature Costs Output

The compressor runs at a fixed speed and draws a fixed volume of air per second. When the air is hotter, that volume weighs less, the turbine burns less fuel at the same firing temperature, and the shaft power falls. The efficiency falls too, because the compressor spends more of the work on hot air. The megawatts that are missing on a hot day are the most valuable megawatts of the year.

Evaporative, Fogging Or Coils

Evaporative coolers and fogging systems spray water into the intake air; the water evaporates and cools the air. They are cheap and effective in dry climates, but they lose most of their effect in humid air, and they consume treated water. Mechanical inlet cooling uses finned coils in the air intake, fed with chilled water or a glycol mixture from a chiller or a thermal storage tank: the air can be cooled whatever the humidity, at the cost of a chiller plant and its power.

The same coils run in reverse in winter. In cold, humid air, ice can form in the inlet filters and on the first compressor stages; warm glycol in the inlet coil - often heated with recovered heat - lifts the air above freezing and keeps the turbine running. Many plants use one coil bank for both duties.

What An Inlet Coil Has To Withstand

An inlet coil sits in the full air stream of the turbine, so its air-side resistance costs output directly: every bit of pressure lost at the inlet is lost power and efficiency, which is why inlet coils are designed for low resistance rather than for compactness. When the air is cooled below its dew point, water condenses on the fins; droplet eliminators downstream of the coil and drain pans under it keep that water out of the compressor. The coil must also not shed anything into the intake - fin material, corrosion products, coating flakes - so materials and coatings are chosen for the site's atmosphere and the cleaning regime.

TECS builds gas turbine inlet coils for cooling and anti-icing duty, with the coil, materials, drain pans and eliminators designed for the turbine's airflow and the site. Send the turbine model, the inlet airflow, the design ambient and humidity and the chilled or heated fluid available, and the proposal shows the coil bank that fits.

In Short

  • A gas turbine loses output as the intake air gets hotter
  • Evaporative and fogging systems: cheap, limited by humidity
  • Chilled-water or glycol coils: independent of humidity
  • The same coils heat the intake air in winter against icing
  • Low resistance, drain pans and droplet eliminators are part of the design
  • TECS builds inlet coils for cooling and anti-icing duty
See the products

What To Send With An Enquiry

  • Gas turbine model and the inlet airflow
  • Design ambient temperature and humidity, summer and winter
  • Target inlet air temperature and the allowed pressure drop
  • Cooling and heating fluid: chilled water, glycol, temperatures and flow
  • Inlet house dimensions and the space for the coil bank
  • Site atmosphere and the corrosion class
Send an enquiry Send us files

Questions We Are Often Asked

How much output does inlet cooling recover?

It depends on the turbine and the climate; cooling the inlet air can recover most of what a heavy-duty turbine loses on a hot day. The turbine maker's performance curves give the figure for a specific machine.

Is evaporative cooling enough?

In a dry climate it gives a good gain cheaply. In humid air the gain shrinks; mechanical coils are chosen where the air is humid or the target temperature is low.

Does the inlet coil reduce output?

Its resistance does, a little, all year round. That is why inlet coils are designed for low resistance and why the net gain is judged with the coil included.

Can the same coil prevent icing?

Yes. In winter warm glycol runs through the coil and lifts the inlet air above freezing; many plants use one coil bank for summer cooling and winter heating.

What happens to the condensate?

It is collected in drain pans under the coil and droplet eliminators downstream stop carry-over into the compressor. Both are part of the coil bank design.

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .