Knowledge base
In short
The right radiator for a generator set is designed from inputs given by the engine maker, the site and the customer, not chosen from a catalogue. The heat load, coolant, ambient conditions, sound limit and space decide the unit. If an input is missing, the radiator is either too large and costly or too small for the hottest day.
The right radiator for a generator set is not a guess and not a catalogue lookup: it is a design from a handful of inputs that the engine maker, the site and the customer provide. Get those inputs right and the radiator is right; leave one out and the unit is either too large and too dear or too small and the engine derates on the first hot afternoon. This guide lists the inputs, where they come from and what each one does to the result.
What The Engine Maker Gives: Heat, Flow, Temperatures, Limits
The engine cooling data sheet is the starting point. For each circuit - one for a small engine, a high-temperature (HT) and a low-temperature (LT) circuit for a large one - it states the heat to be rejected at the site rating, the coolant flow, the coolant temperatures and the pressure drop the engine pump can serve outside the engine. The LT circuit also carries the charge-air temperature the engine needs for its rating and its emissions, which is why it is the most demanding one.
These are not negotiable. The radiator must reject the stated heat at the stated flow, return the coolant at the stated temperature on the design day, and do so within the engine maker's pressure drop limit. A rating at another ambient or altitude means another data sheet; ask the engine maker for the site rating.
What The Site Gives: Ambient, Altitude, Humidity, Air
The design ambient temperature is the single most powerful input: the hotter the site, the larger the radiator for the same engine, and a radiator designed for a mild climate is simply too small in the desert. The temperature to state is the one at which the engine must still deliver its full site rating. Altitude thins the air, so the fans move less mass and the unit needs more airflow or surface. Humidity must be stated as the basis of the design.
The site also says what the air carries - dust, sand, seeds, salt - which decides the coil build and the materials, and where the radiator can stand: on the ground, on a roof, beside the building, with or without a wind that could push the hot discharge back into the intake.
What The Customer Gives: Coolant, Sound, Space, Power
The coolant and its glycol percentage change the heat capacity and the flow behaviour of the liquid, so the mixture is an input, not a detail. A sound limit, with its distance and whether it applies to one unit or to the plant, decides the fans and often the length of the unit. The available space and any transport limit cap the size of the unit; the power supply fixes the fan family.
From these TECS Engineering prepares the design and the datasheet: required and calculated capacity per circuit, flows, temperatures, pressure drops, fans, power, sound levels, dimensions and weights - all at the stated conditions.
A Checklist For The Enquiry
An enquiry that carries the engine cooling data sheet at the site rating, the design ambient, the altitude, the coolant mixture, the sound limit with its distance, the space and the power supply can be answered with a design and a price quickly. One that carries only a kilowatt figure gets a question list first. TECS designs radiators for generator sets of any make - single circuit or LT/HT, horizontal, vertical or V-type - and returns the datasheet, the dimensional drawing, the fan curve and the acoustic data with the offer.
In Short
- The engine data sheet fixes heat, flow, temperatures and the pressure drop limit per circuit
- The design ambient is the most powerful input; altitude and humidity change the air
- Glycol, sound limit, space and power supply shape the unit
- The LT circuit is the most demanding one on a hot site
- The datasheet states every figure at the conditions it belongs to
- TECS designs radiators for any engine make and returns a full design with the offer
What To Send With An Enquiry
- Engine cooling data sheet at the site rating
- Design ambient, altitude and humidity of the site
- Coolant mixture and percentage
- Sound limit and the distance it applies to
- Installation, space and transport limits
- Power supply: voltage, frequency, EC or AC fans
Questions We Are Often Asked
Can a radiator be chosen from the engine's kW alone?
Roughly, for a budget. A real design needs the heat rejection per circuit, the flow and the temperatures from the engine data sheet; two engines of the same output can need very different radiators.
What if the engine data sheet is for sea level and a mild ambient?
Ask the engine maker for the data at the site ambient and altitude - the heat rejection and the rating change with both. TECS can estimate the effect, but the maker's figures are the ones to design to.
Does the radiator carry a margin?
Yes. TECS Engineering covers fouling and uncertainties in the site data, with more on a dusty site, and states the result on the datasheet.
Does the radiator change with EC fans?
The fans do not change the heat; they change how the airflow is delivered. EC fans allow slower speeds for a sound limit and save power at part load.
How long does a radiator design take?
With a complete enquiry, days. The thermal and acoustic design, the drawing and the fan curve are produced together; the time goes into the questions when inputs are missing.
Contact Us
Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on WhatsApp.