Valar Atomics has a county permit for a data center campus that is meant to make all of its own power. On Thursday evening, 12 November, the Carbon County Planning Commission in Utah approved a conditional use permit for the company's Raceway Energy Campus, The Salt Lake Tribune reports. The site is 640 acres of Utah Trust Lands Administration land near Price. The discussion took nearly two hours, and Commissioner Lisa Simmons cast the only vote against.
The company says the campus will generate and use about 3 GW. The Tribune sets that beside roughly 4 GW for the whole state of Utah.
Gas First, Reactors Later
The order of construction is the part that concerns the engine and turbine trade. Valar plans to run the data centers on a natural gas plant first and to build between 40 and 120 nuclear reactors on the site over time. The Tribune's report gives no capacity, no supplier and no start date for the gas plant, and it does not say whether engines or turbines are meant.
What it does give is the cooling concept from the application. The reactor cores are cooled by helium in a closed loop. The data centers use closed-loop systems that are filled once and topped up from time to time. Cory Gardner, head of commercial development at Valar, said the project would use no local water. The plan is to truck water in; if that is not allowed, the company intends to buy private industrial water rights and non-culinary municipal water shares.
The Permits Still Missing
A conditional use permit settles the land use and little else. The list of what Valar still needs is long:
- a building permit and an approved traffic plan from the county,
- an air quality permit from the Utah Division of Air Quality,
- a construction permit from the U.S. Nuclear Regulatory Commission for the reactors.
The county attached conditions of its own. Valar has to file an emergency response plan with the building department, coordinated with the sheriff and the fire marshal, and the permit also covers workforce housing, community engagement and management plans for noise, water and waste. On waste, the application says low-level radioactive material will be kept on site only until it is shipped to a licensed disposal facility.
A Road That Will Not Take The Trucks
About 200 people came to the meeting, but there was no public hearing; County Attorney Christian Bryner said one was not required for this kind of permit. The most practical objection came from the commission itself. Access will at first run over East Coal Creek Road, and Commissioner Kurt McFarlane doubted that the road would stand up to the truck traffic. Gardner answered that the company is willing to upgrade it. In the longer term Valar wants a new road off Airport Road across land of the Bureau of Land Management. The Tribune also mentions a separate Valar proposal, Project Beehive, on 9,000 acres of neighbouring federal land.
No Local Water Means Air Does The Work
For the gas plant that comes first, the water statement is the design brief. Closed loops and no local water mean that the heat of the generating plant and of the data halls leaves through air-cooled equipment. Its size then follows from the site's summer design temperature and its altitude, and the same two figures decide what the gas plant can deliver on the hottest afternoon. With an air permit still open, the number of units and their running hours are not fixed either.
And the road matters more than it looks. Engines, transformers and turbine packages arrive as heavy, oversize loads, so the access route usually has to be settled before the delivery schedule can be believed. Glendale in Arizona recently approved a campus with its own 700 MW gas plant, and there too the local approval came before the air permit.
Sources: The Salt Lake Tribune