Pittsboro Board Clears 36-Engine Gas Plant For Indiana Data Center

Thirty-six gas engines in three halls, built so that a data center does not have to wait for the utility: that is the plant the Board of Zoning Appeals in Pittsboro, Indiana, allowed on Thursday, 12 November. Fox59 reports that three of the five members voted for the special exception and two against, shortly before 10 p.m., at a meeting that had started at 6 p.m. The approval comes with conditions and commitments. Residents who spoke were against it, mostly over noise and the environment, and some booed when the meeting closed.

The applicant is Raeden Acquisitions, LLC. The plant is to stand on about 265 acres of a 625-acre site north of I-74 that is already zoned for a data center campus. The local weekly The Republican wrote on 4 November that the zoning dates from March 2025, when Vantage planned to build there, and that Vantage left the site in July 2025. Raeden has the land under contract.

What The Staff Report Describes

The town's amended staff report of 9 November is unusually specific for a zoning document. It describes a plant of 200 to 300 MW with 36 natural gas reciprocating engines, twelve to a hall, and says more engines are installed than the output needs, so that units can be taken out for maintenance without interrupting supply. The rendering in the file shows the midpoint, a 250 MW power island. Make and arrangement are left open; the report says final engineering and equipment availability will decide them.

  • Power goes behind the meter to the data center through an on-site substation.
  • The engines are cooled by a closed-loop, air-cooled radiator system. Water is needed for one fill of the loop and for the staff restrooms.
  • Each engine has its own SCR and oxidation catalyst with continuous emissions monitoring. The design targets are NOx of 0.05 g/bhp-hr and CO of 0.10 g/bhp-hr, and the plant will run under an air permit from the Indiana Department of Environmental Management (IDEM).
  • The engines are expected to run at 70 to 75% of capacity and have a rated life of about 25 years.
  • The plant and its accessory structures stand more than 1,000 feet from the nearest residence.

According to the report the engines are the initial power supply. As the campus grows it is to be served by or through Hendricks Power Cooperative and Wabash Valley Power Alliance. Jason Green, co-founder and president of Raeden, told The Republican that most of the site would use utility power and that generating part of it on site could give the utility some flexibility.

300 MW And Not One More

The conditions recommended by staff cap the plant at 300 MW; anything larger, in footprint or output, needs a new special exception. A week before the hearing The Republican had reported an initial phase of 400 MW gross at an estimated $2 million per MW, so the staff report sets a lower ceiling than the figure first given. Fox59 does not list the conditions the board adopted. What follows is the staff's list.

Sound is the longest item. The plant must meet the town's limit at the property line, and Raeden is to pay for a baseline survey before construction, for permanent monitoring at the boundary with monthly results on a public website, and for a $1 million bond that the town can call on if a verified exceedance is not corrected. Other commitments cover a road use agreement, an emergency response plan filed with the fire department, an independent engineer whom the town may retain at the applicant's cost, and a removal plan backed by financial assurance. A plant that does not run for 24 months in a row, other than as standby, has to be removed within 12 months. Battery storage is not part of this approval.

One line will interest anyone who has had to change engine supplier halfway through a project. A different number, size or model of generating units does not count as a change to the approval, as long as the plant stays inside its area, burns natural gas, keeps to the sound limit and holds a valid air permit.

The Noise Is Mostly In The Yard

Engines in acoustically treated halls are the easier half of that sound commitment. The radiator fans and the exhaust stacks stand outside, and the staff report treats them separately: ground-level equipment is to be screened where practicable, while elevated components that need open airflow, radiators and stacks by name, only have to carry a neutral, non-reflective finish. With a bond attached to the limit and readings published every month, the fan selection and the position of the radiator field relative to the boundary stop being details. They belong in the acoustic model before the layout is frozen.

The IDEM air permit is still to come, and so is the town's site plan review. Raeden is also working on a community benefit agreement with the town and, according to Green, will not accept local tax incentives. Ohio had a similar engine plant before its siting board in October, EdgeConneX's 30-engine project in New Albany.

Sources: Town of Pittsboro, Board of Zoning Appeals staff report, Town of Pittsboro, meeting agenda, Fox59, The Republican

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir