How much data center load in the United States is real? Latitude Media published one answer on 13 November. Its new research service, Latitude Intelligence, tracks 53 utility territories and sorts the load in each into three stages. About 22 GW is operating. About 120 GW is signed, which Latitude defines as load where the customer has executed an agreement to take service. And 537 GW is what the utilities report as their pipeline.
So the signed figure is about five and a half times what runs today, and the reported figure is about four and a half times what is signed. Georgia Power shows the spread at a single utility: 12.8 GW signed against 80.1 GW reported.
Signed Load Larger Than The System Peak
At three utilities the signed load alone is bigger than today's peak demand. Latitude puts it at 235% of peak at AEP Ohio, 169% at NIPSCO and 145% at PPL. Tech Times, which went through the numbers on 16 November, adds that a signature is not always final. Citing Utility Dive, it notes that Amazon holds a one-time option to reduce its NIPSCO load by 1,200 MW until 31 March 2029.
The same article shows how the stages look inside one utility. From Dominion's own presentation to a PJM subcommittee in September it quotes 12.0 GW under electric service agreements, 9.4 GW under construction letters of authorization and 32.5 GW under engineering letters of authorization. We reported Dominion's 54.9 GW total at the end of October.
33 Months To First Power
The figure a project planner will use first is a different one. Among projects that have been energized since late 2021, Latitude finds an average of 33 months from announcement to first power. The sample is small, 14 projects after outliers were removed, and the article says so.
On the supply side Latitude counts about 37 GW of generation procurements that are open or under consideration at the six largest utilities:
- Dominion is seeking up to 7.3 GW of dispatchable generation, with final submissions due on 18 December and in-service dates running to 2036.
- Georgia Power is pursuing a further 2 to 6 GW.
- AEP has solicitations of 4 GW each for Indiana Michigan Power and Public Service Company of Oklahoma.
- Xcel has procurements in the multi-gigawatt range.
Deadlines This Week And Next Month
Five regional grid operators had until 16 November to answer FERC's show-cause orders on large loads; SPP's answer is due on 20 November. In PJM, utilities cut their near-term load forecasts earlier this month, and Jefferies estimates that the planned backstop procurement could shrink to as little as 630 MW. The next PJM capacity auction runs from 9 to 15 December, according to Tech Times. Georgia Power's next large-load report is expected by the end of November.
Latitude also records resistance at local level. In Ohio, voters decided on 21 local data center measures and chose restriction every time, by its count; Tech Times cites a count of 23 measures from the Statehouse News Bureau, 19 of which passed as restrictions or regulations.
What 33 Months Does To A Power Concept
A service agreement is a signature; it is not energized switchgear. If close to three years pass between announcement and first power on average, and the utility's new plant is dated well into the 2030s, the gap has to be filled by something on the site. That is why so many campuses are now drawn with gas engines or turbines for the first phases and with the standby fleet on top. For the equipment it changes the brief. Plant that was sized for a few test hours a year is asked to run continuously through the hottest weeks, and its ratings, maintenance intervals and cooling have to be specified for that from the start. Our power plants page describes the cooling side of such plant.