The Alberta Utilities Commission has approved a 1,494 MW gas-fired power plant near Indus in Rocky View County, about 3 km east of the Calgary city limit. The plant is to supply a hyperscale data center planned on the same land. The approval was announced on Tuesday, 17 November - one day before the provincial government tabled a bill that would have barred the site, as The Globe and Mail and The Logic both point out.
The developer is a subsidiary of Beacon Data Centers, which the New York venture firm Nadia Partners founded in 2023, according to the Globe. Construction is to start before the end of this year and the plant is forecast to be online in the last quarter of 2027. Neither report says what kind of generating units the plant will use.
A Grid Customer That Had To Build Its Own Supply
When Rocky View County approved the site plan in July 2025, there was no power plant in it. The data center was then expected to draw mainly on the provincial grid. Alberta later restricted grid connections for data centers and told developers to bring their own generation, and the project was reshaped around a plant. The site permit stayed valid, the Globe reports.
The commission's approval covers the power plant only. The data center still needs municipal approval, and Rocky View County has stopped all data center permitting until it has its own regulatory framework. The county cannot stop the plant, though: the commission's decision overrides it.
Indus is not alone. The Globe counts it as the third plant with an on-site data center approved since the province's 2024 data center strategy. The other two are in Sturgeon County near Edmonton: a 1,864 MW plant for Meta's $13 billion data center, and a 902 MW plant, approved last month, that another Beacon subsidiary is developing. The commission is reviewing three more plants tied to data centers, only one of them, in Northern Sunrise County, above 100 MW.
212 M To The Nearest Farmhouse
The Indus site is Class 2 farmland, the best soil class in Alberta, since the province has no Class 1 land. The project boundary lies 212 m from the farmhouse of Creig and Jeannie Antliff, who objected during the review together with more than 20 other neighbors. They raised air and environmental effects, water use, noise and harm to crops and livestock.
Bill 42, tabled on Wednesday, would ban power plants and data centers on Class 1 or 2 land and normally keep them at least 600 m from homes, with municipalities free to ask for more. The Logic adds that the rules would apply to data centers of 10 MW and more and would let the commission review and approve the data centers themselves, not only their power plants. Projects already approved or already before the commission are exempt. The province estimates that about 30% of the projects in development could be affected.
At a boundary 200 m from a house, the noise of a gas plant - exhaust, ventilation, the fans of its cooling equipment - usually becomes the condition everything else is designed around, more than the data center halls next to it. A fixed buffer of 600 m moves that pressure off the equipment and onto site selection. For plant owners in Alberta that is the practical change: fewer arguments in the hearing, fewer sites to choose from. More on power and cooling for data centers is on our applications page.
Sources: The Globe and Mail, The Logic