A utility with about 162,000 customers is asking to build a power plant sized for one customer. Kentucky Power, the American Electric Power subsidiary in eastern Kentucky, filed with the Kentucky Public Service Commission on 13 November for approval of a new combined-cycle gas plant next to its existing Big Sandy gas unit in Louisa, together with a new transmission substation near the EastPark Industrial Park. Both are there to serve TeraWulf's planned Muskie Data Campus in Grayson, which is to grow in phases to 1 GW of contracted demand by 2029.
The company's release gives the plant as 760 MW and leaves out the price. The Kentucky Lantern, which read the filing, reported on 18 November that the plant would cost $2.81 billion, would be rated at up to 769 MW and would enter service in 2031. It would be the first major plant Kentucky Power has built in decades.
Two Years Without The Plant
The dates do not line up, and the utility says so. The campus is to reach 1 GW by 2029, the plant follows in 2031, and in between Kentucky Power intends to buy fossil-fired power from elsewhere, according to the Lantern. In October the company had already dropped an earlier plan for a 450 MW combustion turbine at Big Sandy, WEKU reported at the time. In the new filing it says it looked at a smaller gas turbine and at renewables and concluded that a near-constant data center load needs a denser resource. The Lantern adds that prices for combined-cycle turbines have risen sharply this year on data center demand.
The generation and the transmission work each need a separate Certificate of Public Convenience and Necessity. Kentucky Power says decisions could come as early as mid-2027, depending on the Commission's schedule.
The Bill Question
- TeraWulf pays the applicable service charges and the estimated financing costs of the Big Sandy plant, the utility says.
- Kentucky Power puts the fixed-cost rate offsets for other customers at more than $500 million over the life of the agreement, plus $100 million of winter bill credits for residential customers over ten years from 2029, funded by TeraWulf.
- AEP vice president Alex Vaughn told the Commission in written testimony that existing customers would see no rate increase from the plant, pointing to fuel savings from a more efficient unit and to the revenue from the data center.
Not everyone is convinced. A Boyd County ratepayer who spoke at an October listening session told the Lantern she still worries about residential bills in the long run, and incoming House Majority Whip Josh Bray wants to pass data center ratepayer protections next year after a bill failed this session.
What 2031 Means On Site
We wrote about the contract behind this filing in October, when TeraWulf doubled the Muskie deal to 1 GW. The filing makes the timing plain. For two years or more the campus depends on purchased power and on a transmission build, and that is the period when its own backup plant gets tested for real, not only on commissioning day. Anyone specifying generator sets for a site in that position should assume more running hours than a typical standby duty and size the auxiliaries, fuel logistics and cooling for summer afternoons in the Ohio Valley, not for the test certificate. More on the cooling side of data center generation is on our applications page.
Sources: Kentucky Power (AEP), Kentucky Lantern (via Yahoo News), The Lane Report, WEKU