Ohio Approves Two Behind-The-Meter Gas Plants For Data Centers

Two gas plants that will never sell a kilowatt-hour to the public grid got their state permits in central Ohio on 19 November. The Ohio Power Siting Board approved the 1,350 MW Fairfield Energy Center in Millersport, Fairfield County, and the 800 MW Ashville Energy Center in Pickaway County. Both are behind-the-meter plants, built only to feed the data center campuses next to them, Signal Ohio and the Scioto Post report.

Two Sites, Two Campuses

  • Fairfield Energy Center (case 26-160-EL-BGN): the certificate goes to Fairfield Energy Center, LLC; Signal Ohio names Massachusetts-based Advanced Power as the developer. Along with the 1,350 MW of gas generation the board approved a 1,040 MW battery storage system. The plant takes about 122 acres near State Routes 37 and 204, according to the Scioto Post, and will supply four data centers on a $2.1 billion Vantage Data Centers campus about a mile away (Signal Ohio). The approval carries 36 conditions agreed between the developer and board staff.
  • Ashville Energy Center (case 26-196-EL-BGN): the certificate goes to PowerConneX, whose parent company is the data center developer EdgeConneX. The 800 MW plant sits on about 110 acres along State Route 752 and serves two EdgeConneX data center buildings. The board adopted, with changes, a stipulation between PowerConneX, the village and its staff with 41 conditions, and the company must keep the financial commitments it made to Ashville, the Scioto Post writes.

The board pointed out that its authority ends at the power plants. The data centers themselves are not in its hands.

A Referendum That May Not Count

The Ashville decision came barely two weeks after a local vote went the other way. On 3 November about 82% of Ashville voters rejected the village's development agreement with EdgeConneX, according to Hopewell Heritage Headlines; Signal Ohio puts it at more than 80%. What that result changes now is unclear. Construction on the site is already under way, and the company has told regulators in its filings that the vote has no effect on the plant. Heritage Headlines reports that the board voted unanimously on Ashville and that opponents plan to appeal. Residents had raised air quality, noise and how close the plant is to homes, a soccer field and a playground. Board staff replied that it has to meet the state's safety, emission and noise rules.

In Millersport, residents filled the school cafeteria in August to protest against the plant. Across Ohio this year, all 18 local data center moratoriums and exclusions that went to the ballot were passed, Signal Ohio counts.

Permits Still Open

A siting certificate is not the last piece of paper a plant like this needs. Signal Ohio notes that some of these projects still require separate environmental permits for water discharges or for their backup diesel generators. The second point gets forgotten easily: a campus with its own gas plant still keeps standby sets, and those are permitted, tested and maintained as a system of their own, with their own emission limits and running hours. EdgeConneX has another Ohio plant in the queue, the 30-engine PowerConneX New Albany 3, which had its public hearing in October.

Off the grid, there is no utility to lean on during a forced outage or a hot week when units run derated. The redundancy has to sit in the plant itself - in the number of units, in the cooling of each one, in the spare parts on the shelf. Our page on engine and turbine power plants covers the cooling side.

Sources: Signal Ohio, Scioto Post, Hopewell Heritage Headlines

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir