Texas Issues Air Permit For SpaceX's 35-Turbine Starbase Plant

The Texas Commission on Environmental Quality issued the air permit for SpaceX's gas-fired plant at Starbase on Monday, 16 November, Politico reported a day later. According to a copy that the FracTracker Alliance obtained through a public records request and shared with Politico, the permit covers 35 natural gas turbines with a combined 750 MW on a 444-acre site in the Brownsville area. The plant is to supply a supercomputing facility and will not be connected to the grid. SpaceX puts the project at $24 billion.

The permit allows up to 248 tons of nitrogen oxides a year. That is just below 250 tons a year, the level at which a more thorough review, public hearing included, would apply.

What The Registration Listed

Tech Times, citing The 956 Report, wrote on 13 November that SpaceX filed its registration on 8 September under the Texas standard permit for electric generating units. The filing lists 35 temporary turbines of about 748 MW in total and, as an alternative, eight GE Vernova 7E units of about 708 MW. The reports we read do not say which of the two the issued permit covers. The NOx cap in the filing was 248.86 tons a year. Startup and shutdown emissions do not count toward it, and each turbine is allowed 50 startup and shutdown events a year. The 956 Report worked out that all 35 turbines at full output for a whole year would emit about 458 tons. That is the outlet's own arithmetic, not a TCEQ figure, but it shows that the cap limits running hours as much as hardware.

Teslarati reports that the site lies between Boca Chica Boulevard and the Port of Brownsville. Brownsville took it out of its city limits in August, after SpaceX offered $220 million for water and wastewater projects, and Starbase later annexed it. The Starbase city commission will hear a tax abatement for the project on 9 December.

A Pause That Ended Early

Governor Greg Abbott had told the TCEQ in September to hold data center approvals. The pause was to last until 10 December, the date on which ERCOT is due to report on how the hundreds of proposed data centers would affect the grid. A TCEQ spokesperson told Politico the agency had been informed that ERCOT had gathered the information it needed and had resumed its normal permit review. ERCOT said its audit was still being completed.

Three days before the permit was issued, FracTracker and Public Citizen filed a complaint alleging that SpaceX had started construction without authorization, citing satellite and aerial images of cranes working on turbines at the site between 9 October and 12 November. TCEQ did not answer questions about the complaint, and SpaceX did not respond to Politico. Governor-elect Gina Hinojosa, who takes office in January, wants a moratorium on data centers.

Tons Per Year Decide The Running Hours

For anyone sizing an islanded plant, the tonnage in this permit says more than the 750 MW. A plant that has to stay under a minor-source cap can only run its full fleet for part of the year, so the number of spare units, the start count and the part-load behaviour of each machine end up in the permit file, not only in the operating manual. The Gulf Coast adds its own derating. Whatever the turbines deliver on a cool morning, the rating on a humid summer afternoon and the cooling of the auxiliaries decide what reaches the compute halls.

Mississippi's permit board dealt with a similar case this week, 41 turbines at Southaven. Our page on data center power covers the cooling side of on-site generation.

Sources: Politico (via Yahoo News), Tech Times, Teslarati, Texas Data Center Watch

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir