Kenya's national grid peaked at 2,549 MW on 15 July this year. A Greek developer now wants to moor a gas-fired power barge in Mombasa that would start at 250 MW and could grow to 1,000 MW, mainly to supply AI data centers. Tech-ish, which went through the plan on 17 November, points out that the full build-out would equal about two-fifths of that national peak.
Amaco Energy and ARISE IIP Kenya signed a memorandum of understanding at the Kenya Ports Authority headquarters in Mombasa on 6 November, The Standard reported. The project, which Amaco calls HERCULES, would sit at the Coast Integrated Industrial Park in the Dongo Kundu special economic zone and combine power generation, cooling and data center infrastructure on a 500-acre site. The Standard gives the cost as $700 million (Sh90 billion).
LNG, But No Gas Contract Yet
The first phase is to burn liquefied natural gas supplied through a floating power barge, and the partners say the system is designed to move toward hydrogen and renewables later. In September The Standard and Business Daily reported that Amaco had signed a cooperation agreement with GE Vernova, which is to supply the gas turbines for the barge. No turbine model has been named. At that time the HERCULES project was put at $1.5 billion, and Tech-ish notes that neither company has explained the difference from the November figure.
- Amaco CEO Theodore Theodoropoulos told The Standard the system would be in full operation within 20 to 24 months. He did not say when that period starts.
- Kenya has no gas production and no LNG import terminal, and Amaco has not named a gas supplier.
- The MoU covers technical, commercial, environmental, regulatory and financial assessments. Engineering, approvals, financing and customer contracts are still open, and the plant needs a licence from the Energy and Petroleum Regulatory Authority (EPRA).
- No data center operator has been named as a customer. In September Amaco estimated about 75 MW of base load from heavy industry and 75 to 100 MW from the first data center tenants.
According to Tech-ish, Amaco has also suggested using the cold released when the LNG is regasified to help cool the servers.
A Power Plant That Floats In The Tropics
Barge-mounted plants are an old answer to a site with neither gas infrastructure nor grid capacity, and the hull is the easy part. Mombasa is hot and humid all year, with salt in the air. The turbine output that counts is the output at high ambient temperature, and every heat exchanger on deck has to be specified for a marine atmosphere from the first drawing, not after the first corrosion report. Whether the cold from regasification ever reaches a server hall depends on how the LNG side is laid out, and that side does not exist yet.
A gas supply agreement, an EPRA licence and a named customer are the three things to look for next. Gas turbines for African grids were in our news earlier with the Songon combined-cycle plant in Côte d'Ivoire; more on power plant cooling is on our applications page.
Sources: Tech-ish, The Standard, The Standard (September), Business Daily