Digital Realty Puts Its Own 110 KV Line To Frankfurt Campus Online

Digital Realty no longer has to wait for someone else's cable in Frankfurt. The company said on 17 November that its own 110 kV connection to Digital Park Fechenheim is in operation: a fully underground line of about 16 km from the Karben substation to the campus, designed for up to 300 MVA of grid connection capacity.

The line belongs to Digital Realty. Building and commissioning it took about 20 months, and the company gives the investment only as a triple-digit million-euro sum. Inside Frankfurt more than 70% of the route was laid with trenchless methods, to keep the work away from traffic and residents.

Eleven Buildings, Three Running

At full build-out Digital Park Fechenheim is to have 11 data centers with up to 200 MW of IT capacity. Three are operating and the fourth is scheduled for 2027. Volker Ludwig, Managing Director Central Europe, said in the release that access to power has become a defining factor for digital infrastructure in Frankfurt, and that owning the connection gives the company better visibility when it plans the growth of the site.

The release does not name a grid operator or partner, does not give the exact cost and says nothing about generation on the campus.

Paying For Certainty

A private high-voltage line over 16 km is an expensive way to get power to a site. What it buys is control over the date: the question of when the capacity will be there becomes a construction schedule the owner runs. Germany is working on rules for grid access for data centers and industry, and campus owners who can afford it are evidently not waiting for them.

What the line does not change is the backup on site. An underground cable, however well laid, is still a path to the grid that can fail, and a fault at 110 kV in a buried cable usually takes longer to locate and repair than one on an overhead line. The halls on the campus still need their backup generators, and those generators still need cooling that works on the hottest afternoon of the year. For anyone planning the eight buildings still to come, the useful question is how the 300 MVA will be shared between them, and in what order.

Sources: Digital Realty press release (via StockTitan), Digital Realty newsroom

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir