On 22 July a routine disturbance on the transmission network in the Dominion zone made almost 3.9 GW of data centers drop off utility supply and start running on their own generators. PJM Interconnection calls it the largest load transfer of this kind in its history. On Monday, 16 November, the grid operator filed two proposals with the Federal Energy Regulatory Commission that follow from that day: ride-through rules for very large loads, and a faster way of connecting new plants and new data centers.
A New Class Called LCL
The first filing (docket ER27-522-000) creates a category named Large Computational Load, meaning any load of 50 MW or more. PJM says the threshold follows the definitions FERC and NERC are working on and those other grid operators use. These loads would have to stay connected through voltage and frequency disturbances instead of disconnecting. The proposed effective date is 16 January 2027.
- A new LCL has to prove compliance before it is interconnected and allowed to operate.
- An existing one gets a year, counted from the effective date or from its commercial operation, whichever comes later.
- PJM already serves about 10 GW of such loads and expects up to 30 GW more by 2030.
According to PJM, the July event moved voltages, frequency, power flows and generator output in the Dominion zone and was felt across the Eastern Interconnection. The control room handled it, but PJM says the size and speed of the transfer were a real threat to reliability and safety, and that the new standards would have softened it. Ramp-rate limits and other performance rules are to follow later.
One Study Instead Of Two
The second filing (docket ER27-531-000) is PJM's response to FERC on large loads and co-located loads. At its center is a process PJM calls Fast Energization, which studies new generation and new load together and, by PJM's estimate, cuts the timeline from two years to one. Capitol Fax, summing up Reuters and Bloomberg reports, puts the filing at 1,067 pages.
The PJM summary lists the main changes: a quick initial screening so developers know early whether to go on, readiness and financial requirements that are stricter and come earlier to clear out speculative projects, first-ready first-served kept as the rule, an interim service while network upgrades are built, and room for loads that bring their own generation or can cut their demand. States get a clear view of transmission costs caused by data centers, so they can bill large loads for them. PJM asks FERC to open a 60-day comment period and decide within 120 days.
Not everyone is convinced. Reuters reported that the Data Center Coalition told PJM's board in October that combining the processes could make connections more complicated and in the end slower. Reuters also puts PJM's supply shortfall at about 6.8 GW.
Where The Generator Room Comes In
On 22 July the standby plant did what it was designed to do: the sites saw a grid event, the generators started, picked up the load and kept running. The trouble is that from the grid side 3.9 GW of demand vanished at once. Under the new rule a site has to stay on the network through faults it would earlier have escaped by going to its own sets. For the electrical designer that means revisiting UPS, transfer and protection settings. For the mechanical side it may mean fewer nuisance starts, and the plant that does start still has to carry full load in the hottest week of the year. We covered the NERC standards for data center loads in October; standby power and cooling are on our data center page.
Sources: PJM Inside Lines (ride-through), PJM Inside Lines (Fast Energization), Capitol Fax