Sydney has long been the default answer when a data center operator plans for Australia. In the second issue of the Australian Data Centre Forecast Report, published by Data Centres Australia with research from DC Byte at the end of October, Melbourne has overtaken it in total pipeline. Data Center Knowledge went through the figures on 20 November. Melbourne's tracked capacity rose by 1.7 GW to 10.7 GW over six months, while Sydney's fell by 3.6 GW to 7.8 GW.
The Numbers Behind The Pipeline
Nationally, DC Byte tracks 26.8 GW across all phases, 5.2 GW more than in April. Most of it is paper: 19.6 GW is early-stage, meaning the projects do not yet have land, power and permits all secured. Committed capacity, where DC Byte is confident the project will be built, rose from 3.1 to 5.2 GW. Capacity under construction, defined as data halls in mechanical and electrical fit-out, doubled to 0.4 GW. Operational capacity rose by only 0.1 GW, to 1.6 GW in 163 facilities.
- Only four operating Australian data centers exceed 100 MW today. Of the 97 projects in the pipeline, 52 announce more than 100 MW, 24 of them in Victoria and 19 in New South Wales.
- Capacity outside the two big cities now makes up 31% of the pipeline, against 19% two years ago, with early-stage projects in Queensland, Tasmania, South Australia and Western Australia.
- The report forecasts 3.9 GW of operational capacity nationally by 2030.
Why Sydney Shrank
The report links Sydney's drop to energy constraints in the city, less certain approval timelines and recent policy announcements; most of the fall came out of early-stage projects. Melbourne moved 1.2 GW from early-stage to committed, against 0.7 GW in Sydney, which the authors put down to Victoria's faster Development Facilitation Program. They also warn that Victoria has recently announced new policies for data centers and appears to have paused approvals ahead of the November state election.
The analysts quoted by Data Center Knowledge agree that Australia does not lack generation before 2030 so much as connections. IDC's William Lee sees the connection works for large campuses in Western Sydney and Melbourne's west as the largest delivery risk, and wants proof of a signed connection agreement, an energization date and terminal-station schedules before calling a project committed. JLL's Matthew Lee expects metropolitan power for very large sites in both cities to run out at some point.
What A Regional Site Has To Bring Along
The move into the regions changes the plant list. A campus at the end of a long line, far from a metropolitan substation, leans harder on its standby generators, and hot inland summers put the generator cooling to the test on exactly the days the grid is under stress. That is a different specification from a Sydney colocation hall. Melbourne's connection problems are not new either: we reported in October on the suspended 66 kV works at NextDC's M3 campus. More on standby power and cooling is on our data center page.
Sources: Data Centres Australia / DC Byte, Data Center Knowledge