How do you supply 6 GW to a site in rural southeastern Arizona whose local cooperative owns a fraction of that? Arizona's attorney general Kris Mayes wants that answered first. On 19 November she asked Cochise County to postpone its 9 December vote on the special use permit for SpaceX's planned AI supercomputing campus near Willcox until state and federal agencies have reviewed the project, AZFamily and KJZZ report.
The Size Of It
SpaceX announced on 12 November that it plans to spend more than $74 billion on two supercomputing sites, about $50 billion of it in Arizona and more than $24 billion at Starbase in Texas, Fortune writes, citing Reuters. The Arizona campus would sit on 747 acres next to the Willcox Playa, about 80 miles east of Tucson. According to AZFamily it needs 1.5 GW at start-up and 6 GW at full build-out. KJZZ compares the final figure with the all-time peak of Arizona Public Service this year, 9,164 MW across all its customers.
APS would not serve the site. Fortune reports that power would come through the Sulphur Springs Valley Electric Cooperative and the Arizona Electric Power Cooperative (AEPCO), and that SpaceX says the nearby Apache Generating Station, a coal and gas plant, would grow from about 1 GW to more than 6 GW. The permit application lists $3.6 billion of grid upgrades.
What The Attorney General's Letter Questions
Mayes' letter, as AZFamily summarises it, reads the numbers differently. It says the start-up load alone is 62% larger than AEPCO's entire owned and contracted generation, that Apache produces roughly 625 MW, and that SpaceX has not said how a gap of 4.5 GW would be closed. Other points in the letter:
- The application states 7 to 10 acre-feet of water a year for a campus without evaporative cooling, but that figure leaves out the water used to make the power. The letter puts the withdrawal of a 1 GW gas plant running around the clock at 3.6 to 6.8 million gallons a day. The site lies in the Willcox Active Management Area, set up two years ago against groundwater depletion.
- About 6,150 Tesla Megapack battery units would be on site, outside any fire district.
- Up to 5,500 workers at peak construction, and heavy trucks on rural two-lane roads.
- Possible interference with Fort Huachuca and Army electronic testing on the Playa.
If the county votes anyway, Mayes asks that the permit only take effect once all state and federal approvals are in hand, that building permits wait as well, and that the full 6 GW be reviewed rather than one phase at a time. She is holding her own town hall at Cochise Elementary School on 3 December.
Power First, Then Everything Else
Whatever Cochise County decides, the electrical question will set the pace. A gigawatt-scale campus far from a strong grid usually ends up with large on-site or nearby generation, and in Willcox that plant would run through Arizona summers, when gas turbines and engines lose output just as the IT load wants the most cooling. The Texas half of the plan already has its air permit for 35 gas turbines, and APS has its own 4,000 MW gas plan in front of regulators. Cooling for engine and turbine plants is covered on our power plants page.
