Siemens Energy To Supply Two SGT-800 Turbines For TAURON Będzin CHP

TAURON Ciepło, the heat subsidiary of the Polish utility TAURON, has picked a Siemens Energy consortium to supply two turbine islands for a new gas-fired cogeneration plant at Będzin Łagisza in Upper Silesia. Each island is built around an SGT-800 gas turbine of 49.9 MW electrical output. TAURON disclosed the decision and the signed contracts in a stock exchange filing on 4 November; Turbomachinery Magazine reported the details on 20 November.

What The Filing Says

The contractor is a consortium of Siemens Energy Sp. z o.o. in Warsaw and Siemens Energy AB in Finspång, Sweden. Two agreements were signed:

  • Supply: EUR 94.5 million net for the two turbine sets with the rest of the equipment and installations that make up each island, plus documentation, advice during installation and commissioning, and consumables.
  • Service: EUR 49.9 million net for inspections, overhauls and repairs to the contractor's schedule and for clearing faults, running for 12 years from the takeover of each island.

Delivery is due 150 weeks after signing for one island and 154 weeks for the other, which the filing puts at September and October 2029. TAURON can charge penalties for late delivery and for missed guaranteed parameters, capped at 20% of the net value of each agreement. The company says the terms are standard for contracts of this kind.

Replacing Coal Heat At Łagisza

The new unit is meant to take over the heat that a retired coal unit at Łagisza used to deliver, Turbomachinery Magazine writes, as part of TAURON's plan to build or modernise more than 1.1 GW of heat capacity by 2030. Earlier Polish reports cited by the magazine had described a unit of about 120 MWe and 140 MWt, later about 100 MWe and 120 MWt with a heat storage tank and an electrode boiler, enough heat for around 62,000 apartments. The 2026 filing gives neither the heat output nor the total investment, and it does not say whether the storage tank and electrode boiler are still part of the scheme. A larger 400 MWe gas-steam project at the site had been dropped in 2025.

For Siemens Energy it is one more order in a year that ended with a record EUR 164 billion backlog.

Why Two Units, Not One

Splitting a district heating source into two mid-size turbines is the usual answer when the plant has to follow a heat load that swings between a January morning and a July night. One unit can be down for its overhaul in summer while the other carries the hot-water demand, and the electrode boiler and storage tank, if they stay in the design, take the peaks and the hours when power prices make running the turbines pointless.

The 150-week delivery time is worth noting too. Medium industrial turbines are not exempt from the queues the large frames face, and a utility that wants heat from gas before the end of the decade has to sign in 2026. The balance of plant - heat recovery, the cooling of auxiliaries and lube oil, the stack - has to be ordered against the same calendar. Our cogeneration page covers the cooling side of CHP plants.

Sources: Turbomachinery Magazine, TAURON Polska Energia current report (money.pl)

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir