Ohio State's Campus CHP Plant Opens Three Years Late At $585 Million

How does a campus power plant budgeted at under $300 million end up above $585 million? Ohio State University's Combined Heat and Power Plant on John Herrick Drive in Columbus began operating in September 2026, three years after its planned 2023 opening, and its final cost is now expected to exceed $585 million, WOSU reported on 20 November. That is about twice the original estimate.

From $279 Million To $585 Million

According to WOSU, the plant was first estimated at $279 million, later revised to $289.9 million. Construction began in 2020. The university names materials, inflation, design, cost estimating and project management as the reasons, together with the firing of the original contractor by ENGIE Buckeye Operations. Ohio State says it is responsible for $349 million and ENGIE for the remainder, and that ENGIE is still working out the final figure.

The numbers moved in steps. In October 2025 the student paper The Lantern quoted a budget of $420.8 million and an expected start in April 2026. The university spokesperson said then that ENGIE Buckeye Operations, the construction manager, carries 80% of any overruns. Ohio State Energy Partners manages the project; the Ohio Power Siting Board approved it in September 2020 after an application filed in 2019.

More Than A Power Plant

The plant supplies electricity and heat to parts of the campus. The Lantern describes it as part of a district heating and cooling loop with a central chiller facility, with an 8,000-ton cooling system that can be expanded to 13,000 tons and hot-water and chilled-water networks for the Midwest and West Campuses. A 2021 university update had promised savings of $10 million a year, break-even after about 12 years and 30 to 35% lower carbon emissions. The plant burns natural gas, which students and faculty groups have opposed.

Where Campus CHP Projects Lose Time

The reasons Ohio State gives will sound familiar to anyone who has built a CHP plant inside an existing site. The generating units are rarely the problem. The time goes in the tie-ins: steam and hot-water lines that have to be cut into networks that cannot be shut down, chilled-water piping across a live campus, and a contractor change halfway through, which on its own can cost a year while the new team re-checks what the old one built.

A campus also cannot accept a winter without heat, so on projects like this commissioning usually has to run alongside the existing supply, and that stretches it out. Owners planning similar district energy schemes should put the interfaces and the contractor's financial strength at the top of the risk list, not the equipment delivery. More on cooling for cogeneration plants is on our applications page.

Sources: WOSU Public Media, The Lantern

Other News

Contact Us

Send us the heat duty, the fluid temperatures and flow rates, the ambient conditions and the installation limits. We answer with a design proposal - or write to us on .

I am interested in
TECS
AXON Technic
One enquiry reaches both companies of the group.
Send us files

TECS Engineering factory, Menemen, İzmir